HR Construction Group successfully completed the full renovation of 754 guestrooms and associated corridors at the Baltimore Marriott Waterfront hotel in downtown Harbor East, Baltimore. The extensive renovation occurred while the hotel maintained their occupancy and included 577 shower conversions, 637 barn door installations and new electrical and Kohler plumbing fixtures throughout. New carpet, tile, paint and wall-covering finishes highlight the upgraded and newly installed FF&E package. HRCG oversaw the duration of the job including change orders while meeting the demands of the project schedule and exceeding customer expectations over the life of this hotel project renovation.

CONTACT US

PROJECT DESCRIPTION

  • Category: Hospitality
  • Location: Baltimore, MD
  • Owner: USB Realty Investors LLC
  • Architect: Baskervill
  • Contract Value: $12.5 Million 
  • Duration: 8 Months

PROJECT DETAILS

  • Renovated 754 guestrooms and associated corridors including 21 suites and 28 ADA rooms
  • Completed 577 tub to shower conversions
  • Put in all new Kohler plumbing fixtures
  • Installed new lighted Majestic Mirror in bathroom with new switches/sensors
  • Painted and inserted wall covering finishes throughout
  • Laid new tile at the foyers and within bathrooms
  • Placed new carpet in all guestrooms and corridors
  • Installed 637 custom made barn doors and sliding hardware tracks in bathrooms
  • Put in new entry and closet door hardware
  • Liquidated all existing room furniture and replaced with new FF&E package